Construction Plan Review Time Guidelines
The City will review all plans in conformance with state and local laws.
The following represents review times for conforming construction plans:
Subdivision |
1st Submittal |
2nd Submittal |
3rd Submittal |
Plan Revision |
---|---|---|---|---|
2-5 lots | 3 weeks | 2 weeks | 2 weeks | 2 weeks |
6-50 lots | 4 weeks | 3 weeks | 2 weeks | 2 weeks |
51 + lots | 5 weeks | 3 weeks | 2 weeks | 2 weeks |
Any project involving a new or highly modified pump station | 5 weeks | 3 weeks | 2 weeks | 2 weeks |
Site |
1st Submittal |
2nd Submittal |
3rd Submittal |
Plan Revision |
---|---|---|---|---|
Minor Addition | 2 weeks | 2 weeks | 2 weeks | 2 weeks |
Site Within Master Planned Subdivision | 2 weeks | 2 weeks | 2 weeks | 2 weeks |
Average Site Plan | 3 weeks | 2 weeks | 2 weeks | 2 weeks |
Large Site Plans: Shopping Center/ Multi-Family | 4 weeks | 3 weeks | 2 weeks | 2 weeks |
Power Center | 6 weeks | 4 weeks | 2 weeks | 2 weeks |