Construction Plan Review Time Guidelines

Review Times for Conforming Construction Plans

Subdivision1st Submittal2nd Submittal3rd SubmittalPlan Revision
2 to 5 lots3 weeks2 weeks2 weeks2 weeks
6 to 50 lots4 weeks3 weeks2 weeks2 weeks
51 or more lots5 weeks3 weeks2 weeks2 weeks
Any project involving a new or highly modified pump station5 weeks3 weeks2 weeks2 weeks


Site1st Submittal2nd Submittal3rd SubmittalPlan Revision
Minor Addition2 weeks2 weeks2 weeks2 weeks
Site Within Master Planned Subdivision2 weeks2 weeks2 weeks2 weeks
Average Site Plan3 weeks2 weeks2 weeks2 weeks
Large Site Plans: Shopping Center/ Multi-Family4 weeks3 weeks2 weeks2 weeks
Power Center6 weeks4 weeks2 weeks2 weeks