Construction Plan Review Time Guidelines
Review Times for Conforming Construction Plans
Subdivision
1st Submittal
2nd Submittal
3rd Submittal
Plan Revision
2 to 5 lots
3 weeks
2 weeks
2 weeks
2 weeks
6 to 50 lots
4 weeks
3 weeks
2 weeks
2 weeks
51 or more lots
5 weeks
3 weeks
2 weeks
2 weeks
Any project involving a new or highly modified pump station
5 weeks
3 weeks
2 weeks
2 weeks
Site
1st Submittal
2nd Submittal
3rd Submittal
Plan Revision
Minor Addition
2 weeks
2 weeks
2 weeks
2 weeks
Site Within Master Planned Subdivision
2 weeks
2 weeks
2 weeks
2 weeks
Average Site Plan
3 weeks
2 weeks
2 weeks
2 weeks
Large Site Plans: Shopping Center/ Multi-Family
4 weeks
3 weeks
2 weeks
2 weeks
Power Center
6 weeks
4 weeks
2 weeks
2 weeks
Construction Plan Review Time Guidelines
Request a City Service
Online Payments
Waste Pickup
Forms & Permits
Government Meetings
Your Property
Government Websites by
CivicPlus®
Arrow Left
Arrow Right
[]
Slideshow Left Arrow
Slideshow Right Arrow