Project Description: Stormwater system improvements in several neighborhoods are needed to increase the system capacity and provide a higher level of protection.
Project Budget: $4,749,600
Specific Project Details:
1. Allen Dr and Fresno Dr Drainage Improvements: Survey complete; design to be complete by late Summer 2023; construction start Winter 2023.
2. Benefit Rd Drainage Improvements: Survey complete; 50% design underway; anticipate construction start Fall 2023.
3. Blanche Dr Drainage Improvements: Survey and wetland delineation complete; 50% design, easement acquisition, and environmental permitting underway; anticipate construction start Winter 2023.
4. Crestwood Manor Drainage Improvements: Evaluation project priority
5. Deal Dr Drainage Improvements Phase 2: Evaluation project priority
6. Gruen St Drainage Improvements: Evaluation project priority
7. Jarvis Rd Drainage Improvements Phase 2: Evaluation project priority
8. Myers & Hoover Drainage Improvements: Survey complete; 100% design underway; anticipate construction start Summer 2023
9. Perry St Drainage Improvements: Survey complete; 90% design underway; anticipate construction start late Summer 2023
10. St. Brides Rd Drainage Improvements: Survey complete; design on hold pending drainage analysis underway; anticipate construction start Spring 2024. Assessing potential easement acquisition opportunity
11. Willis St Drainage Improvements: Preliminary design and survey underway