Project Description:
Halifax Lane Outfall Improvements Phase 2- Provide improvements to the 10-year storm level of protection from the outfall channel and pipe within the drainage area. Work includes the upstream improvements from Bainbridge Blvd. up toward A Street will include approximately 1,250 ft. of ditch and channel widening to include pipe crossing D Street and B Street.
D Street Drainage Improvements-provide improvements to the roadside drainage along D Street and intersections from 207 D Street south to the intersection with Decatur Street. Improvements to include gutters, drainage structures, and drainage pipes.
Design Start: Spring 2017
Design Completion: Fall 2023
Project Budget: $2.85 million