Volvo Parkway at Battlefield Boulevard Intersection

In Design

Phase 1 of the project will provide an eastbound right turn lane and re-striping to create three left turn lanes, two through lanes, and one exclusive right turn lane. Public Works is proceeding with right-of-way coordination. City will seek appropriation of funding from City Council to adjoin funding from VDOT received early. Phase 2 of project will include a second right turn lane, re-striping through and left turn lanes, and modifications to the median.

Project Design Start: June 2020

Projected Design Completion: July 2022

Project Budget: $1.35 million