Citizen Information
ACTIVE
Stormwater & Drainage Projects
- Below is a listing along with maps that describe active stormwater & drainage projects.
-
Please note: Budget includes design, property acquistion for right of way and easements, and construction costs
Last update: August 15, 2008 (Projects are updated quarterly.)
QUICK VIEW -LOW-RES
Clickable map of Active Stormwater & Drainage Projects
html & .gif image (540 kb)
TEXT REPORT
Alphabetical listing
Print list of Active
Stormwater & Drainage Projects
pdf (26 kb)
DETAILED VIEW- HI-RES
Clickable map of Active Stormwater & Drainage Projects
pdf (2,5 MB)
Clickable map of Active Stormwater & Drainage Projects
pdf (1.9 MB)
Stormwater & Drainage Improvement Areas
Recently Completed Projects
BUTTS STATION OUTFALL
Widen outfall drainage ditch south of Butts Station Road near Clearfield Ave intersection. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $250,066 | |
| Funding Source: Developer Pro Rata Drainage Funds | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
CAMELOT DRAINAGE PHASE II
Provide new drainage pipe outfall for the Camelot subdivision lake system. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $1,520,000 | |
| Funding Source: Capital Improvement Budget FY07 to FY09 | |||
| Construction Start Date:: TBD | Completion Date: TBD | ||
CAMPOSTELLA/WAKE AVE. DRAINAGE IMPROVEMENTS
Provide new Quad Box Culvert crossing under Campostella Road near Wake Ave. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $1,200,000 | |
| Funding Source: Storm Water Fee – CIB FY07 to FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
CAMPOSTELLA ROAD DRAINAGE IMPROVEMENTS PHASE 1
Provide ditch improvements from Campostella Road Military Highway. If funding from Campostella/ Wake Ave and Phase I allow, phase II provides a new culvert crossing under Military Highway Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $37,500 & residual from Campostella/Wake Ave | |
| Funding Source: Storm Water Fee – CIB FY07 to FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
CREST HARBOR DRAINAGE IMPROVMENTS
Replace storm water pipe on Mains Creek Rd. Replace pipe at outfalls and provide tide flex valves on outfall pipes. Regrade ditch along Mullen Rd. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $500,000 | |
| Funding Source: City Capital Improvement Budget – FY07 to FY09 | |||
| Construction Start Date:: TBD | Completion Date: TBD | ||
DELIA DRIVE DRAINAGE OUTFALL IMPROVEMENTS
Reroute drainage from Expressway SWM Basin to new outfall. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $355,000 | |
| Funding Source: Council Appropriation – April 10, 2007 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
DEWALD ROAD DRAINAGE IMPROVEMENTS
Improve drainage by regrading existing roadside ditches, replacing pipe culverts and storm systems, and enlarging outfall ditch. Construction schedule will be established when design is complete and easements are acquired.
| Project Managed By: City | Status: Construction | Budget: $170,000 | |
| Funding Source: Council Appropriation – Nov 21, 2006 | |||
| Construction Start Date: 7/08 | Completion Date: 10/08 | ||
DUNEDIN AREA DRAINAGE IMPROVEMENTS
Provide drainage from undelevoped area adjacent to Dunedin subdivision to existing storm water system. Construction schedule will be established when design is complete.
| Project Managed By: City | Status: In Design | Budget: $250,000 | |
| Funding Source: City Capital Improvement Budget FY08 to FY09 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
FENTRESS OUTFALL
Improve 2,700 feet of drainage ditch from Mount Pleasant Rd through Back Road. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $272,630 | |
| Funding Source: Developer Pro Rata Drainage Funds | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
FERNWOOD FARMS DRAINAGE IMPROVMENTS
Regrade ditches along and Maple Shore Dr and Fernwood Farms Rd. Construction schedule will be established after after easements are acquired.
| Project Managed By: City | Status: In Design | Budget: $250,000 | |
| Funding Source: City Appropriation – March 2008 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
FOREST LAKES OUTFALL IMPROVEMENTS
Install a new culvert and reshape outfall to provide better storm water drainage.
| Project Managed By: City | Status: Construction | Budget: 95,000 | |
| Funding Source: City Capital Improvement Budget (Neighborhood Drainage) FY08 | |||
| Construction Start Date: 9/08 | Completion Date: 10/08 | ||
GEORGE DR OUTFALL IMPROVEMENTS
Regrade large outfall ditch in Washington Manor.
| Project Managed By: City | Status: Construction | Budget: $100,000 | |
| Funding Source: City Capital Improvement Budget (Neighborhood Drainage) FY08 | |||
| Construction Start Date: 9/08 | Completion Date: 10/08 | ||
HALIFAX ST OUTFALL IMPROVEMENTS
The project includes the removal of existing pipe system and the installation of a larger pipe system to handle the stormwater runoff from several areas within Chesapeake and City of Norfolk. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: Study | Budget: $1,000,000 | |
| Funding Source: City Capital Improvement Budget FY09 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
LOXLEY GARDENS DRAINAGE IMPROVEMENTS
Provide drainage improvements to relieve ponding at three residential intersections and improve 2,300 feet of outfall channel from Loxley Gardens through Gilmerton Rd. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $450,000 | |
| Funding Source: City Capital Improvement Budget FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
MONEY POINT STORMWATER IMPROVEMENTS
Improve outfall and storm water system in Money Point including BMP installation. Construction scheduled will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $455,667 | |
| Funding Source: City Funds and State/Federal Matching Funds Grant | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
MURRAY DR/GREENHAVEN AREA OUTFALL IMPROVEMENTS
Improve outfall ditch and install larger culverts. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $2,100,000 | |
| Funding Source: City Capital Improvement Budget FY09 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
PARTRIDGE/CLOVERDALE AREA DRAINAGE IMPROVEMENTS
Improve drainage by installing valley gutter/edging and pipe system. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $600,000 | |
| Funding Source: City Capital Improvement Budget FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
POINDEXTER ST OUTFALL IMPROVMENTS
Improve the stormwater system for the Poindexter corridor from Bainbridge to the outfall by replacing existing outfall and constructing a BMP. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $1,000,000 | |
| Funding Source: City Appropriations – March 2008 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
RAINTREE SUBDIVISION DRAINAGE
Replace pipe crossing Winslow Ave and regrade and reset driveway pipes.
| Project Managed By: City | Status: Construction | Budget: $21,000 | |
| Funding Source: City Capital Improvement Budget (Neighborhood Drainage) FY08 | |||
| Construction Start Date: 10/08 | Completion Date: 12/08 | ||
SCENIC BLVD DRAINAGE IMPROVEMENTS
Regrade ditch along Scenic Blvd from Denver St to Washington Dr and reset driveway pipes. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $260,000 | |
| Funding Source: City Capital Improvement Budget FY09 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
SHILLELAGH ROADSIDE DITCH RELOCATION
Regrade 2000 feet of ditch and reset driveway pipes. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $600,000 | |
| Funding Source: City Capital Improvement Budget FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
SHIPS CROSSING OUTFALL DITCH
Regrade outfall ditch between Ships Crossing subdivision and Shipyard Road.
| Project Managed By: City | Status: Construction | Budget: $38,400 | |
| Funding Source: City Capital Improvement Budget (Neighborhood Drainage) – FY08 | |||
| Construction Start Date: 10/08 | Completion Date: 12/08 | ||
SUNRAY DRAINAGE OUTFALL – PHASE III
Provide drainage crossing improvements under Norfolk and Southern Railroad tracks.
| Project Managed By: City | Status: In Design | Budget: $627,000 | |
| Funding Source: City Capital Improvement Budget FY04 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
WASHINGTON DRIVE DRAINAGE IMPROVEMENTS
Regrade ditch along both sides of Washington Drive from E Street to new development improvements and rest driveway pipes. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $560,000 | |
| Funding Source: City Capital Improvement Budget FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
WATERS ROAD DITCH AND SHOULDER IMPROVEMENTS
Install to new pipe and provide shoulder to the west side of Waters Road fro mWashington Drive to Chattanooga Street. Construction schedule will be established when design is completed.
| Project Managed By: Consultant | Status: In Design | Budget: $3,042,000 | |
| Funding Source: Council Appropriation – February, 2008 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
WILLOW LAKE/LAKE SHORE CULVERT REPLACEMENT
Install larger culverts to improve storm water drainage. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $700,000 | |
| Funding Source: Council Appropriation – April 10, 2007 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
YADKIN ROAD OUTFALL IMPROVEMENT
Replace existing culvert under Norfolk and Southern Railroad near Yadkin Road, add a detention pond/BMP and improve outfall. Construction schedule will be established when design is completed.
| Project Managed By: City | Status: In Design | Budget: $300,000 | |
| Funding Source: Council Appropriation – April 10, 2007 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
YADKIN ROADSIDE DITCH IMPROVEMENTS
Regrade ditch and reset driveway pipes along Yadkin Road. Construction schedule will be established when design is completed..
| Project Managed By: City | Status: In Design | Budget: $250,000 | |
| Funding Source: City Capital Improvement Budget FY08 | |||
| Construction Start Date: TBD | Completion Date: TBD | ||
RECENTLY COMPLETED PROJECTS
BOXWOOD DR. DRAINAGE IMPROVEMENTS
Repair valley gutter, regrade ditch, and replace drainage outfall pipe on Boxwood Drive.
| Project Managed By: City | Status: Completed | Budget: $534,738 | |
| Funding Source: Storm Water Fee – City Wide Undesignated Drainage Funds | |||
| Construction Start Date:: 10/2007 | Completion Date:: 2/2008 | ||
CAMELOT DRAINAGE PHASE I
Provide new a new entrance for Old Deep Creek Blvd in order to remove the existing culvert and provide new ditch opening on the outfall for the Camelot subdivision lake system.
| Project Managed By: City | Status: Completed | Budget: $80,000 | |
| Funding Source: Capital Improvement Budget – FY07 to FY 08 | |||
| Construction Start Date:: 4/2008 | Completion Date: 7/2008 | ||
OAK GROVE OUTFALL
Improve 500 feet of drainage channel from Green Tree Rd to Chesapeake Arboretum.
| Project Managed By: City | Status: Completed | Budget: $93,572 | |
| Funding Source: Developer Pro Rata Drainage Funds | |||
| Construction Start Date: 8/2007 | Completion Date: 1/2008 | ||
PORTLOCK DRAINAGE OUTFALL
Provide for replacement of the drainage pipe system under and parellel to Bainbridge Blvd (north of Freeman)
| Project Managed By: City | Status: Completed | Budget: $500,000 | |
| Funding Source: City Funds and State/Federal Matching Funds Grant | |||
| Construction Start Date: 1/2008 | Completion Date: 6/2008 | ||
City of Chesapeake, Virginia