Subdivision Construction
Inspection & Acceptance Process

How do I get my subdivision inspected and accepted by the city?

Prerequisites:

  1. A Subdivision Plan must be approved by Public Works.

To begin construction:

  1. Complete the Resident Notification form. The resident notification form shall be completed and mailed/delivered to the adjacent property owners thirty (30) days prior to commencing construction.

  2. Obtain the Land Disturbing Permit.

  3. Contact Public Works Development Construction rhepler@cityofchesapeake.net or (757) 382-6384 no later than forty-eight (48) hours prior to land disturbing activities so a pre-construction meeting and inspection can be scheduled, according to the recommended construction sequence. Any deviation from approved construction plan shall be addressed by a plan revision or a field change request.

  4. Obtain the Right-of-Way Permit & Stormwater Permit (if required).

  5. Plat Recordation must occur prior to the Utility and Streets & Drainage acceptance.

  6. Utility Final/Activation (Utility Activation detailed process)

    • Complete the water and sewer improvements on the approved plans and the PFM.

    • Request a Utilities substantial inspection upon completion of improvements which will cause Public Works to perform a punch list inspection.

    • Submit the activation package including the Utilities Construction Record Drawings ('As-Builts') (flowchart). Click here to see examples of Utility Construction Record Drawings

    • Complete the punch list items.

    • Upon approval of the activation package, the Public Works Inspector will notify the contractor to take water samples per Flushing and Disinfection Policy.

    • Request Utility final inspection.

    • City accepts water and sewer improvements and activates utilities.

  7. Streets & Drainage Final Acceptance

    • Complete all streets & drainage improvements on the approved plans and the PFM.

    • Request a video inspection of closed storm drain systems two (2) weeks prior to installing the first lift of asphalt.

    • Request a streets and drainage substantial completion inspection upon completion of the physical improvements according to the approved plans.

    • Submit the Streets & Drainage Acceptance Package including the Streets & Drainage Construction Record Drawings (As-builts). Click here to see examples of Streets & Drainage Construction Record Drawings

      Note: This is a full set containing each plan sheet.

    • Complete the punch list items.

    • Request the streets & drainage final inspection.

    • City release performance bond and accepts the streets & drainage public improvements.