Nina Dr. Area Drainage Improvements Phase I
DESIGN COMPLETE
This project will include pipe upgrades to the 10-year storm along San Salvador Dr. to the outfall ditch downstream of Lisa Cove Way. Construction expected to begin in Spring 2021.
- Project Design Start: Spring 2018
- Project Design Completion: July 2020
- Project Budget: $1.2 million