Neighborhood Drainage Improvement Projects
ONGOING PROJECTS
The City is undertaking several neighborhood drainage projects, including:
- Allen Dr. and Fresno Dr. Drainage
Survey complete; design underway; construction expected to begin Winter 2021 - Benefit Rd. Drainage Improvements
Survey complete; design underway; construction expected to begin Fall 2021 - Blanche Dr. Drainage Improvements
Survey and wetland delineation complete; design underway; construction expected to begin Winter 2021
- Crestwood Manor Drainage Improvements
Scoping underway - Deal Dr. Area Drainage Improvements Phase I
Phase I construction underway; approximately 95% complete - Deal Dr. Area Drainage Improvements Phase II
Scoping underway - Myers & Hoover Drainage Improvements
Survey complete; design underway; construction expected to begin Summer 2021 - Perry St. Outfall Improvements
Survey complete; design underway; construction expected to begin Fall 2021 - St. Brides Rd. West Drainage Improvements
Survey complete; design underway; construction expected to begin Fall 2021 - Wedgewood Drive Drainage Improvements
Design and right-of-way acquisition complete; construction expected to begin Summer 2021