Straight to Defect (100% Complete)
If all subdivision improvements are 100% complete, a developer can elect to avoid posting a Performance Bond and go straight to Defect Period.
Requirements:
- All improvements reflected on subdivision plan are to be complete and any
punchlist items resolved. - Subdivision Plat is ready for recordation.
- Final Subdivision Plat must be reviewed and approved by Directors of Development and Permits and Planning.
- Plat processing fees are paid.
- Lot Grading Certification is submitted.
- Total inspection fees paid.
- All Streets and Drainage Final Acceptance items must be submitted and approved:
- Defect Bond (Must be approved by City Attorney)
- Construction Record Drawings
- Right-of-Way Monument Certification
- Street Light Installation payment or Cost Agreement (if required)
- Utilities Final Inspection (Activate Water & Sewer)
- Streets & Drainage Final Inspection is performed.
- Record Plat.
- Subdivision then goes to 2-year Defect Period.