Subdivision Construction Inspection and Acceptance Process
How do I get my subdivision inspected and accepted by the city?
Prerequisites:
- A Subdivision Plan must be approved by Development & Permits Department, Development Engineering Division.
To begin construction:
-
Complete the Resident Notification form. The resident notification form shall be completed and mailed/delivered to the adjacent property owners thirty (30) days prior to commencing construction.
-
Obtain the Land Disturbing Permit.
-
Contact Development & Permits, Development Engineering Division rhepler@cityofchesapeake.net or (757) 382-6384 no later than forty-eight (48) hours prior to land disturbing activities so a pre-construction meeting and inspection can be scheduled, according to the recommended construction sequence. Any deviation from approved construction plan shall be addressed by a plan revision or a field change request.
-
Obtain the Right-of-Way Permit & Stormwater Permit (if required).
-
Plat Recordation must occur prior to the Utility and Streets & Drainage acceptance.
-
Utility Final/Activation (Utility Activation detailed process)
-
Complete the water and sewer improvements on the approved plans and the PFM.
-
Request a Utilities substantial inspection upon completion of improvements which will cause Public Works to perform a punch list inspection.
-
Submit the activation package including the Utilities Construction Record Drawings ('As-Builts') (flowchart).
-
Complete the punch list items.
-
Upon approval of the activation package, the Development & Permits Development Construction Inspector will notify the contractor to take water samples per Flushing and Disinfection Policy.
-
Request Utility final inspection.
-
City accepts water and sewer improvements and activates utilities.
-
-
Streets & Drainage Final Acceptance
-
Complete all streets & drainage improvements on the approved plans and the PFM.
-
Request a video inspection of closed storm drain systems two (2) weeks prior to installing the first lift of asphalt.
-
Request a streets and drainage substantial completion inspection upon completion of the physical improvements according to the approved plans.
-
Submit the Streets & Drainage Acceptance Package including the Streets & Drainage Construction Record Drawings (As-builts).

Note: This is a full set containing each plan sheet. -
Complete the punch list items.
-
Request the streets & drainage final inspection.
-
City release performance bond and accepts the streets & drainage public improvements.
-