Inspections for New Commercial Building Construction
| INSPECTION TYPE | When performed | Permit Required | Performed by | |
|---|---|---|---|---|
| FOOTING |
After installation of reinforcement and before placement of concrete | Building Permit In some cases, foundation permit is required |
Building Inspector |
|
| Slab if applicable |
After approval of all subtrade ground work and after installation of reinforcement, vapor barrier and perimeter insulation (if required) and prior to placement of concrete. | Building Permit | Building Inspector |
|
| Plumbing Slab if applicable |
After installation of below-slab plumbing piping and prior to covering with slab base material | Plumbing Permit for slab only |
Plumbing Inspector |
|
| Electrical Groundwork Slab, if applicable |
After installation of conduit and conductors in trenches or in slab base material and prior to backfilling trench or covering with slab base material | Electrical Permit for slab only |
Electrical Inspector |
|
| Electrical Rough-In Wall | Prior to concealment | Electrical Permit | Electrical Inspector |
|
| Electrical Rough-In Ceiling | Prior to installation of ceiling tiles | Electrical Inspector |
||
| Plumbing Rough-In drain, waste, vent and water distribution piping | Prior to concealment | Plumbing Permit | Plumbing Inspector |
|
| Water Line | Prior to backfilling trench, inspect the water line from the building to the meter location | Plumbing Inspector |
||
| Sewer Line | Prior to backfilling trench, inspect the sewer line from the building to the sewer lateral. | Plumbing Inspector |
||
| Gas Pressure Test | Inspections are included as follows: Gas pipe groundwork, gas product line for installations utilizing propane. Prior to concealment |
Gas Permit | Mechanical Inspector |
|
| Mechanical Rough-In |
After installation of air handling duct, before placement of duct, dishwasher hood, spray paint booth and duct, walk-in cooler/freezer, and prior to concealment. | Mechanical Permit | Mechanical Inspector |
|
| Framing | The following inspections may be performed at the same time of framing inspections; after approval of all subtrade rough-ins and prior to concealing walls (hanging drywall) Above ceiling: after installation of ceiling grid and prior to installing dropped ceiling panels. Spray-on/Fireproofing: after installation of ceiling grid and all above ceiling equipment and prior to installation of dropped ceiling panels. Draftstopping: after installation of required draftstopping material. Firestopping: after installation of required firestopping material and prior to concealment. Insulation: prior to concealment. | Building Inspector |
||
| Propane Tank | Need Fire Prevention approval prior to obtain Fire Permit | Fire Permit | Fire Prevention Inspector |
|
| Storm Drains | Storm Drains | Permit not required |
Engineering letter (see procedure for on-site inspections must be submitted prior to obtain a certificate of occupancy |
|
| Backflow Device | After installation of backflow prevention devices | Plumbing Permit for backflow device | 3rd party testing and inspections required | |
| Plumbing Final | After completion of all piping and installation of all plumbing fixtures, equipment and appliances and before final building inspection. | Plumbing Permit | Plumbing Inspector |
|
| Electrical Final | After complete installation of electrical system and prior to the final building inspection | Electrical Inspector |
||
| Elevator (if applicable) |
Mechanical Permit for elevator | Elevator Inspector |
||
| Mechanical Final | After complete installation of all mechanical equipment and before the final building inspection. | Mechanical Inspector |
||
| Fire Inspection | Upon installation of the fire protection or hazardous materials system (See Fire Permit for list of systems) (note: pre-final hydro/air test & visual inspect. reqd. prior to covering aboveground or underground sprinkler piping & underground hazmat piping & tanks) Also Fire Inspection required for most buildings for issuance of Certificate of Occupancy |
Fire Permit (See Permit Application for Systems that require a permit prior to installation) Submit 3 sets of plans with Fire Permit application to Fire Prevention for review & approval. Pick up approved package from Fire Prevention when notified & pay for and obtain permit from Development & Permits |
Fire Prevention Inspector from Fire Department. To request an inspection, please call the Fire Inspection Request Line at (757) 382-8211 with 48 hrs. prior notice |
|
| Landscape | Must submit the landscape plan to the Arborist for an approval prior to requesting a building final inspection. | Building Inspector or Arborist |
||
| Asbuilts | Must submit an asbuilts site plan to the Department of Public Works prior to issuance of certificate of occupancy. | Department of Public Works (757) 382-6304 |
||
| Flood Certification | Must submit a flood certification if the property is in the flood zone. FEMA Elevation Certificate & Instructions |
Department of Development & Permits, Code Enforcement Administrator |
||
| Special Inspections |
Must submit the complete Special Inspections to the Plan Examiner: Statement of Special Inspections Form
Special Inspections Guidelines & Procedures |
Department of Development & Permits, Plan Examiner |
||
|
||||
| Print above chart - Required Steps |
||||
The City will make every effort to provide inspections on your requested date. However, please be aware, the Virginia Uniform Statewide Building Code allows two working days from the date of request to perform the inspection.
You can request your inspections by mail, email, phone, fax (contact info below) or online.
Please provide the below information when requesting inspections:
Permit Number
Property Address
Type of Inspections - See Required Steps
![]()
Contractor’s Name
Phone Number
Requestor Name
All requested inspections will be directed to and processed by the City’s Customer Contact Center at 757-382-CITY (2489). You may also submit your inspection request online via the City of Chesapeake Customer Contact Center.
We still accept requests by fax and email.
Next-business-day inspection requests by phone, fax, mail or email must be received by 3:00 p.m. Monday through Friday.
Any requests after 3:00 p.m. on Friday, Saturday and Sunday will be scheduled for Tuesday.Request by Phone
All inspections by phone will be directed to the City’s Customer Contact Center at 382-CITY (2489).
Operator on duty - MON– FRI, 8:00 a.m. to 5:00 p.m.Request by Fax
By completing our inspection request form, you may fax your inspection requests at
757-382-8448 or 757-382-8555.Request by Mail
By completing our inspection request form, you may mail your inspection requests to:
City of Chesapeake
Department of Development & Permits
P.O. Box 15225
Chesapeake, VA 23328Request by email
You may send us an email to request your inspection(s). Our email address is develop-permits@cityofchesapeake.net
Request Online
The following are instructions to assist you in creating a valid request for an inspection:
- Go to www.cityofchesapeake.net website and click on the Customer Contact Center Request a City Service link.
The next screen will display a heading of Service Type with an
indicating a drop-down menu. Click on the
and then click on Inspection Request.
This selection will now take you to the intake screen for your inspection request. Appearing on this first screen will be
Request a City Services
Service Type: Inspection RequestProvide the address of the site you want to have inspected. For commercial sites, there are additional spaces for information to be provided that may be of assistance to the inspector such as the building name, floor and unit number. Now click on the Next button.
In the appropriate boxes, indicate the permit number associated with your inspection request (Alpha character followed by 9 numerical characters). If requesting a building, electrical and plumbing inspection, you will need to indicate that permit number in the space provided by each category.
Once you have entered the permit number, you may now select the type of inspection you need. If you have multiple inspections for that permit, you only need to hold down the CTRL key and click each type of inspection.
Specify the date you want the inspection as indicated, MM/DD/YYYY. Example: 01/20/2012.
If there are any special instructions to the inspector about this inspection, please list them in the appropriate box. Items that would fit into this field would be that the neighbor on the left has the key to the house or the lock box combination is 4567.In the event that we need to contact the person making the request, please provide the Requestor's Name and daytime phone number where indicated.
Click on the Review button. Your request will be displayed for you to review and edit, start over or submit options. When you are ready to make your request complete, click the Submit button and you’re done.
To save steps in the future, go directly to online Inspection Request.
-
The Department of Development & Permits provides the citizen a daily online Inspection Results listing.
-
ONLINE INSPECTIONS RESULTS STATUS.
The status will be updated every day after 2:00 p.m The inspection status will remain on-line for seven working days only. If the requested inspection is performed more than 7 days ago, call 757-382-6018 for your inspections results.
- Normally, the Department of Inspections’ inspectors will leave a yellow inspection card at the job site to notify the permit holder if the inspection is approved or rejected with the information of the reason for rejection.